## [[Risk Action Plan]] >[!question] [[Risk Description|Description]] > (Causes, Consequences, Implications) >Schedule to be Resource and Cost Loaded and the company currently does not have the capabilities to do so. [[BUILT RIGHT CONSTRUCTION]] does not have the ability to evaluate the subcontractors schedule. Bowser is know for providing misinformation to Peach. >[!question] Key Assumptions > This requirement was not made know to [[BUILT RIGHT CONSTRUCTION]] until after the Phase 1 of the contract was executed. >[!question] [[Current Controls]] >Currently the Subcontractor would be required to provide this information through their scheduling resources. >[!info] [[Sources of Information]] > > > ![[Section 01 32 16.20.1.01.A.3]] >[!info] Attachments > >[!danger] Calculated Risk Factor >[[Semi-Quantitative Assessment]] >Consequence = >Likelihood = >(consequence + likelihood)-(consequence x likelihood) >[!success] [[Risk Mitigation Strategy]] > >[!success] Possible Additional Actions > | Response | Effectiveness | Cost | | ---- | ---- | ---- | | | | | | | | | | | | | >[!success] Comments & Recommendations > >[!example] Status >