5. Submit to Engineer updated progress schedule, together with network diagram (when required), reports, and other schedule-related documents required to accompany the updated progress schedule, in accordance with Electronic Communication Protocols, and Submittal Procedures. Also submit updated progress schedule in its native format generated by the scheduling software, transmitted using the transmission method indicated in Electronic Communication Protocols.