3. Resource and cost - loaded progress schedules will be reviewed by Engineer within 10 days of Engineer’s receipt, and Engineer’s comments will be transmitted to Contractor.
4. Make revisions required in accordance with Engineer’s comments and resubmit to Engineer within 10 days of Contractor’s receipt of Engineer’s comments.