### 3.2 Annual Review and Reimbursement/Reconciliation.
Energy-related cost savings shall be verified, measured and/or calculated as specified in *Schedule C - Savings Measurement and Verification Plan; Post-Retrofit M&V Plan; Annual M&V Reporting* and *Schedule B - Baseline Energy Consumption; Methodology to Adjust Baseline* and a report provided within ninety (90) Days of the end of the year for the previous year for each anniversary of the Guarantee Period Start Date.
If the Energy and Cost Savings achieved during any guarantee year are less than the Guaranteed Energy and Cost Savings as defined in *Schedule A - Savings Guarantee*, Contractor shall pay EPIC WATER AUTHORITY an amount equal to the deficiency.
Contractor ==shall remit such payments to EPIC WATER AUTHORITY within ___ Days== of written notice by EPIC WATER AUTHORITY of such monies due. In no event shall credit for excess savings be used to satisfy saving guarantees in past or future years of this Exhibit H.