### 2.1 Guarantee Period Start Date. The Guarantee Period Start Date shall be the first day of the month after the month in which all schedules are in final form and accepted by EPIC WATER AUTHORITY and ==Contractor shall have delivered a notice to EPIC WATER AUTHORITY that it has installed and commenced operating all the Equipment (specified in a Schedule to be determined when the [[Phase 2 Work and Pricing Amendment]] is negotiated);== and EPIC WATER AUTHORITY has inspected and accepted said installation and operation as evidenced by a writing between the Parties. Notwithstanding anything to the contrary in this Exhibit H, ==the Guarantee Period Start Date shall not occur unless and until all Equipment installation is completed by Contractor in accordance with the terms and conditions of the [[Contract Documents]].== The Guarantee Period Start Date shall be confirmed in a writing between EPIC WATER AUTHORITY and Contractor.