[[Key Completion Times|Key Completion Time]]:
1. Exhibit A, section entitled “Key Completion Times”, is deleted in its entirety and replaced with the following:
[[Key Completion Times]]:
- A. [[Phase 1]]:
- [[Milestone|Milestone 1]], submittal of Basis of Design Report, shall be 605 Days from the start date specified in the Notice to Proceed.
- [[Milestone|Milestone 2]], submittal of [[Lump Sum Price]], shall be 678 Days from the completion of [[Milestone|Milestone 1]].
- B. [[Phase 2]]: If EPIC elects to proceed to [[Phase 2]], [[Key Completion Times]] are to be determined and set forth in the [[Phase 2 Work and Pricing Amendment]].
> [!danger]- Language Replaced by Amendment 2
> [[Key Completion Times]]:
> A. [[Phase 1]]:
> [[Milestone|Milestone 1]], submittal of Basis of Design Report, shall be 605 Days from the start date specified in the Notice to Proceed.
> [[Milestone|Milestone 2]], submittal of [[Lump Sum Price]], shall be 455 Days from the completion of [[Milestone|Milestone 1]].
> B. [[Phase 2]]: If EPIC elects to proceed to [[Phase 2]], [[Key Completion Times]] are to be determined and set forth in the [[Phase 2 Work and Pricing Amendment]].
> [!danger]- Language Replaced by Amendment 1
>
>**[[Key Completion Times]]:**
>A. [[Phase 1]]:
>[[Milestone|Milestone 1]], submittal of Basis of Design Report, shall be 350 Days from the start date specified in the Notice to Proceed.
>[[Milestone|Milestone 2]], submittal of [[Lump Sum Price]], shall be 700 Days from the completion of [[Milestone|Milestone 1]].
>B. [[Phase 2]]: If EPIC WATER AUTHORITY elects to proceed to [[Phase 2]], [[Key Completion Times]] are to be determined and set forth in the [[Phase 2 Work and Pricing Amendment]].