## [[Risk Action Plan]]
### [[Risk Description|Description]]
Due to limited geotechnical investigation data from the preliminary design phase, there is a [[threat]] that additional borings may be required during detailed design, which may lead to design delays and potential foundation redesign.
> [!abstract]- Risk Analysis — Key Assumptions & Current Controls (click to expand)
>
> **Key Assumptions:**
> - Preliminary boring data from the site investigation phase was limited in scope and may not reflect subsurface conditions across the full pump station footprint.
> - Foundation design is proceeding on the basis of existing data pending additional investigation results.
>
> **Current Controls:** None at identification. Additional boring program authorized November 2025.
> [!abstract]- Sources of Information & References (click to expand)
>
> **Sources:**
> - Preliminary geotechnical investigation report (pre-design phase)
>
> **Contract References:**
> - [[EXHIBIT C - General Conditions]]
> - [[Executed Contract]]
### [[Risk Mitigation Strategy]]
Authorize and complete a supplemental boring program targeted at the pump station foundation footprint. Review results against design assumptions before finalizing foundation design.
### Possible Additional Actions
### Comments & Recommendations
Risk was identified early in detailed design due to the limited number of borings performed during the preliminary phase. The supplemental program authorized by [[Princess Peach]] in November 2025 provided the additional data needed to validate the foundation approach. Results confirmed suitable bearing capacity with no redesign required.
### Status
- [ ] [[2026-01-15]] Risk resolved — Boring results confirm suitable bearing capacity. Foundation design validated by [[Yoshi]]. No foundation redesign required. ^status-2026-01-15
> [!abstract]- Status History (click to expand)
>
> - [x] [[2025-11-06]] Additional boring program authorized by [[Princess Peach]]. 12 borings scheduled for December 2025. ^status-2025-11-06
> - [x] [[2025-08-10]] Risk identified — preliminary boring data insufficient for pump station foundation. Supplemental geotechnical investigation to be scoped. ^status-2025-08-10